By now the base for the tower which is the responsibility of the building owner should have been already completed. But because the workers equipment for drilling holes was damaged, the base construction work halted. Then afterwards, they repaired their equipment and they have completed the base materials. Below pictures shows some of the completed that was taken 2 days ago.

This is the place where the drilling guys were drilling the I-beams and plates.

Yesterday, they were telling me that they are coloring the beams and the plates. So today they should be assembling the base. Let’s see what happens. However, our tower engineer has broken his leg and is hospitalized. So I expect the tower work to be delayed, how many days I don’t know. I should be getting the tower construction receipt and other documents. For now I have to wait and see. Will be posting updates later.